Project Timeline
 DESCRIPTION OF WORK  DATE*
Town Council Authorization to contract EIR/Design consultants Jan. 6, 2016
Notice to proceed Jan. 11, 2016 
Alternatives Jan. 22, 2016 
Public input on alternatives: 4-6pm, Suite Z (Minaret Village Mall) Jan. 29, 2016
Alternative selection Feb. 2016
Preliminary design Mar. 2016
EIR meeting & public input on preliminary design: 4-6pm, Suite. Z Mar. 18, 2016
Presentation to design review committee & Planning/Economic Dev. Commission April 13, 2016 
Town Council presentation May 4, 2016
Notice of Preparation/Scoping public review period June 2-July 1, 2016
EIR scoping meeting with Planning and Economic Development Commission, 2pm June 8, 2016
Preparation of Draft EIR July-Sept., 2016
Public review of Draft EIR  Oct.-Nov., 2016
Preparation of Final EIR January, 2017
Public Hearing and EIR certification by PDEC January, 2017
Construction documents Mar. 2017
Advertise for construction phase April 2017
Bid opening  May 2017
Town Council award May 2017
Notice to proceed May 2017
Begin construction June 2017
Ribbon Cutting Halloween 2017
* Schedule subject to change  