Project Timeline
 DESCRIPTION OF WORK  DATE*
Town Council Authorization to contract EIR/Design consultants Jan. 6, 2016
Notice to proceed Jan. 11, 2016 
Alternatives Jan. 22, 2016 
Public input on alternatives: 4-6pm, Suite Z (Minaret Village Mall) Jan. 29, 2016
Alternative selection Feb. 2016
Preliminary design Mar. 2016
EIR meeting & public input on preliminary design: 4-6pm, Suite. Z Mar. 18, 2016
Presentation to design review committee & Planning/Economic Dev. Commission April 13, 2016 
Town Council presentation May 4, 2016
Notice of Preparation/Scoping public review period June 2-July 1, 2016
EIR scoping meeting with Planning and Economic Development Commission, 2pm June 8, 2016
Preparation of Draft EIR July-Sept., 2016
Public review of Draft EIR  Oct.-Nov., 2016
Preparation of Final EIR January, 2017
Recreation Commission and Mammoth Lakes Recreation consider funding options May 2, 2017 
Public Hearing and EIR certification by PDEC May 10, 2017
Town Council considers certification of EIR May 17, 2017
Town Council considers funding certification & direction to proceed with project  May 17, 2017
Authorize final construction documents June, 2017
Town Council award partial grading and utilities work August, 2017
Town Council award contract for roof structure January, 2018
Town Council award contract for buildings, ice rink and site work April, 2018
Begin construction May, 2018
Ribbon Cutting Halloween 2018
* Schedule subject to change  